GOVERNMENT OF INDIA
MINISTRY OF HOUSING AND URBAN AFFAIRS
RAJYA SABHA
UNSTARRED QUESTION NO. 2619
ANSWERED ON 16/03/2026
PROPOSALS FOR HYDERABAD METRO RAIL PHASE-II
2619. SMT. RENUKA CHOWDHURY:
Will the Minister of HOUSING AND URBAN AFFAIRS be pleased to state:
(a) whether the Central Government has received and examined the proposal for
Hyderabad Metro Rail Phase-II, if so, since when the proposal has been pending with
the Centre;
(b) the reasons for the delay in granting in-principle or final approval to the project,
despite submission and its stated importance for urban mobility in a major
metropolitan city;
(c) whether the proposal is stalled at any specific level within the Central Government,
including inter-ministerial consultations or appraisal committees; and
(d) whether the Central Government has sought clarifications or imposed additional
conditions that have contributed to the delay, if so, the details thereof?
ANSWER
THE MINISTER OF STATE IN THE MINISTRY OF HOUSING AND URBAN AFFAIRS
(SHRI TOKHAN SAHU)
(a) to (d): The proposals of Hyderabad Metro Rail Phase-II (76.4 km) and Hyderabad Metro
Phase-II (B) (86.1 km) were received in the Ministry from Government of Telangana on
04.11.2024 and 20.06.2025 respectively. The Metro Rail projects are highly cost intensive,
which undergoes thorough appraisal process and examination which entails seeking
additional information / clarifications at different levels in Central Government as per
relevant provisions of Metro Rail Policy, 2017. The approval of project depends upon
outcome of such appraisal process, feasibility of project and availability of the resources.
*****