GOVERNMENT OF INDIA
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
LOK SABHA
UNSTARRED QUESTION NO. 6336
ANSWERED ON 2ND APRIL, 2026
UPGRADATION OF NH-183 FROM KADAVOOR-ANJILIMOODU STRETCH
IN KERALA
6336. SHRI KODIKUNNIL SURESH
Will the Minister of ROAD TRANSPORT AND HIGHWAYS
सड़क परिवहन औि िाजमार्ग मत्रं ी
be pleased to state:
(a) whether the Government has approved proposals for the
development, widening or upgradation of the stretch of NH-183 from
Kadavoor to Anjilimoodu passing through districts including Kollam
and Alappuzha;
(b) if so, the details of the financial sanctions granted, including year-
wise allocations and the estimated project cost;
(c) the present status of the project including stages such as survey,
Detailed Project Report, land acquisition, tendering and construction;
(d) whether the Government will provide the official alignment plan
and details of the approved route alignment for the said stretch of NH-
183;
(e) whether any proposals for realignment, bypasses or additional
connectivity improvements have been received from the State
Government or local authorities and if so, the details thereof; and(f) the timeline for commencement and completion of the project and
the steps taken to expedite the development of this stretch of NH-
183?
ANSWER
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (f) A proposal for widening to a 4-lane configuration for the
section from Kollam Bypass Junction (Km 4/200) to Anjilimoodu (Km
58/570) of NH-183 in the State of Kerala has been considered and the
project is now planned with a 4-lane configuration within an effective
Right of Way (ROW) of about 20 metres so as to minimise demolition of
large numbers of structures. Contribution of the State Government is
being sought in terms of utility shifting costs, including land
acquisition for the utility corridor or reimbursement of State
component of Goods and Services Tax, whichever is preferable for the
State Government.
Land acquisition for the project has been initiated. Further action,
including consideration of sanction, tendering and construction, will
be taken as per extant procedures, subject to availability of land,
utility shifting and requisite statutory clearances.
*****