GOVERNMENT OF INDIA
MINISTRY OF STATISTICS AND PROGRAMME IMPLEMENTATION
LOK SABHA
UNSTARRED QUESTION NO. 5469
TO BE ANSWERED ON 25.03.2026
INFRASTRUCTURE AND PROJECT MONITORING DIVISION
5469. SHRI UTKARSH VERMA MADHUR:
Will the Minister of STATISTICS AND PROGRAMME
IMPLEMENTATION be pleased to state:
(a) whether the Infrastructure and Project Monitoring Division (IPMD)
has identified the Central Projects (like National Highways or Railway
Overbridge) related to Kheri area which are lagging behind their set
schedules;
(b) whether there has been any increase in the cost of the said
projects due to the delay; and
(c) the details of instructions issued by the Government to the
concerned departments to complete the said projects within the
stipulated timeline?
ANSWER
MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF
STATISTICS AND PROGRAMME IMPLEMENTATION; MINISTER OF
STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF PLANNING
AND MINISTER OF STATE IN THE MINISTRY OF CULTURE [RAO
INDERJIT SINGH]
(a) and (b): The Ministry of Statistics & Programme Implementation
(MoSPI) is mandated to monitor the status of Ongoing Central Sector
Infrastructure Projects costing Rs. 150 crore and above based on
data reported by Line Ministries/ Departments/ Implementing
Agencies and the same is being undertaken through online web
monitoring system called PAIMANA (Project Assessment
Infrastructure Monitoring and Analytics for Nation-Building).
Accordingly, the State-wise details of all ongoing infrastructure
projects are available in the Flash Report published by this Ministry
on the website https://ipm.mospi.gov.in/ReportPage. However, the
data is monitored at the State level.(c): All stakeholders (Infrastructure Line Ministries/ Departments) are
regularly being apprised of their project execution and slippages on
the basis of data analytics available on PAIMANA, for any required
intervention in managing the project execution at their end. Further,
regular coordination with stakeholders through monthly review
meetings and other communications contribute to the evidence-
based monitoring. In addition to, the login credentials providing
access to the customized dashboards are already shared with all Line
Ministries/ Departments, thereby giving them direct access to the
portal for review of the project progress.
Other major steps taken by the Government of India to mitigate the
delays and expedite the infrastructure projects include the Periodic
review of projects under PRAGATI meetings through video
conferencing by Hon’ble Prime Minister, and rigorous project
appraisal.
*****