GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
NABARD – RIDF XV- SPS Nellore District - “Providing BT to Road from
NP Road to Thoderu village via Marpur village” - Granting of post facto
Extension of Agreement time upto 1.6.2011 without Penalty - Orders -
Issued
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
PANCHAYAT RAJ AND RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 147 Dated:27.1.2012
Read the following:
1. G.O.Rt.No.1845,PR&RD (Progs.II) dept, Dated. 11.12.2009
2. From the Chief Engineer , Panchayat Raj , NABARD,
Hyd, Lr.No. NB16/ Thoderu/ RIDF XV/ NLR/ 2009
dated 30.11.2011.
*****
ORDER:
In the circumstances reported by the Chief Engineer, Panchayat Raj,
NABARD, Hyderabad in his letter 2nd read above, Government after careful
examination of the proposal, hereby grant post facto Extension of Agreement
Time up to 01.06.2011 i.e for (155) days without imposing liquidated damages,
in respect of work, “Providing BT to road from NP Road to Thoderu Village via
Marpur Village” in SPS Nellore District sanctioned under NABARD RIDF XV as
the delay is not attributed to the contractor.
2. The Chief Engineer, Panchayat Raj, NABARD, Hyderabad, is requested to
take necessary action accordingly.
3. A copy of this order is available on the Internet and can be accessed at
www.ap.gov.in/goir.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer, Panchayat Raj, NABARD, Hyderabad.
The Superintending Engineer, Panchayat Raj, Nellore district.
Copy to:
The PS to Minister (Panchayat Raj & RWS)
Sc / Sf
//FORWARDED::BY ORDER//
SECTION OFFICER