GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
PMGSY- EOAT – Phase VIII – Nalgonda District - Package No.AP-VIII-1039
- “Providing BT on road from PWD road Nagarjuna sagar to
Nagarjunapeta, Nalgonda District” – Post Facto Extension of Agreement
Time without penalty from 2-9-2010 to 30-6-2011 – Orders – Issued.
-----------------------------------------------------------------------------------
PANCHAYAT RAJ & RUAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 180 Dated: 04-02-2012.
Read the following :-
From the ENC(PR), PMGSY, Hyd.Lr.No.W12/DEE.IV/PMGSY Ph
VIII-1309/Nagarjunasagar/NLG/2011,Dt. 25.08.2011.
>><<
O R D E R
In the circumstances reported by the Engineer-in-Chief, Panchayat
Raj, PMGSY, Hyderabad in his letter read above, Government after
examination of the proposal hereby accord Post Facto Extension of
Agreement Time from 2-9-2010 to 30-6-2011 for a period of 300 days as
requested by the ENC, PR, PMGSY, Hyderabad without penalty as the delay
is not attributed to the contractor due to Forest Department Clearance in
respect of work “Providing BT on road from PWD road Nagarjuna sagar to
Nagarjunapeta, Nalgonda District” under PMGSY Phase VIII Package No. AP
VIII -1309.
2. The Engineer-in-Chief, Panchayat Raj, PMGSY, Hyderabad shall take
necessary action accordingly.
3. A copy of the order is available on the Internet and can be accessed
at www.ap.gov.in/goir.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Engineer-in-Chief, Panchayat Raj, PMGSY, Hyderabad
The Superintending Engineer (PR), Nalgonda District.
Copy to:
The PS to Minister for PR &RWS.
Sc/Sf.
//FORWARDED::BY ORDER//
SECTION OFFICER