GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
PMGSY- Phase VIII - Ananthapur District – “Providing BT to the road from
Muchukota to Cikkepalli (via) Varadaipalli (M), Ananthapur District” -
Revised Administrative Sanction along with excess tender premium and
price escalation - Accorded - Orders- Issued.
-----------------------------------------------------------------------------------
PANCHAYAT RAJ & RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 182 Dated: 04-02-2012.
Read the following:-
1) G.O.Rt.No.68, PR&RD. (Progs.II) Department, Dt.27-2-2009.
2) From the ENC(PR), PMGSY , Hyd, Lr.No.W22/PMGSY- Phase
VIII 0261/2010,Dt. 14.9.2011.
<<>>
O R D E R:
In the reference first read above, Orders were issued according
Original Administrative Sanction for an amount of Rs.51.30 lakh in respect
of the work “Providing BT to the road from Muchukota to Cikkepalli (via)
Varadaipalli (M), Ananthapur District” under PMGSY Phase VIII.
2. In the references 2nd read above, the Engineer-in-Chief, Panchayat
Raj, PMGSY, Hyderabad has requested the Government to accord Revised
Administrative Sanction for an amount of Rs.52.15 lakh as against the
Original Administrative Sanction of Rs.51.30 lakh in respect of the work
“Providing BT to the road from Muchukota to Cikkepalli (via) Varadaipalli
(M), Ananthapur District” due to excess tender premium and price
escalation under PMGSY Programme, Phase VIII.
3. Government after careful examination of the proposal, hereby
accord Revised Administrative Sanction for an amount of Rs.52.15 lakh
(Rupees Fifty two lakh and fifteen thousand only) indicating the GOI Share
of Rs.48.82 lakh (Rupees Forty eight lakh and forty two thousand only)
and State share of Rs.3.33 lakh (Rupees Three lakh and thirty three
thousand only) in respect of the work “Providing BT to the road from
Muchukota to Cikkepalli (via) Varadaipalli (M), Ananthapur District” as
against the Original Administrative Sanction of Rs.51.30 lakh (Rupees
Fifty one lakh and thirty thousand only) due to excess tender premium
and price escalation to be borne by the State Government towards State
share under PMGSY, Phase VIII. The amount chargeable is as follows:
OAS cost of above work : Rs.51.30 lakh
Now RAS required as follows:
a) Amount chargeable from PMGSY Ph.VII : Rs.48.82 lakh
b) Amount chargeable from State Govt.
Share towards Excess Tender Premium : Rs. 3.33 lakh
Total RAS required ( a+b) : Rs.52.15 lakh
4. The Engineer-in-Chief, Panchayat Raj, PMGSY, Hyderabad is
requested to check the price escalation calculations to arrive at the actual
price escalation amount and take necessary action accordingly.
p.t.o.::2::
5. This order issues with the Concurrence of the Finance Department vide
their U.O.No.33697/715/2011/Expr.PR&RD, dt.27.12.2011.
6. A copy of this order is available on the internet and can be accessed
at www.ap.gov.in/goir .
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Engineer-in-Chief, Panchayat Raj, PMGSY, Hyderabad
The Superintending Engineer, PR, Ananthapur District.
The District Treasury Officer, Ananthapur District.
The Accountant General, Andhra Pradesh, Hyderabad.
Copy to:
The P.S to Minister (PR &RWS)
Finance (Expr.PR&RD) Dept.
Sc/Sf.
//FORWARDED::BY ORDER//
SECTION OFFICER