GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
PRED – RIAD – TFC – Warangal District – Construction Of Bridge across
Vattivagu on R/f Lakshmipuram of Penugonda PWD road - Granting of post
facto Extension of agreement time upto 27.11.2011 with out imposing the
liquidated damages - Orders – Issued
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
PANCHAYAT RAJ AND RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 234 Dated:13.2.2012
Read the following:
1. G.O.Rt.No.84, G.A (RIAD) Department dt.25.02.2009.
2. From the CE, PR, NABARD, Hyd, Lr.No. R.10/ DEE.IV/
RIAD–TFC/Warangal/2010, dt. 11.01.2012
*****
ORDER:
In the circumstances reported by the Chief Engineer, Panchayat Raj,
RIAD, Hyderabad in her letter 2nd read above, Government after careful
examination of the proposal, hereby grant post facto Extension of Agreement
Time up to 27.11.2011 i.e for (331) days without imposing any penalty, in
respect of work, “Construction of Bridge across Vattivagu on R/f Lakshmipuram
of Penugonda PWD road” in Warangal district, sanctioned under TFC as the
delay was not attributed to the contractor.
2. The Chief Engineer, Panchayat Raj, RIAD, Hyderabad, is requested to
take necessary action accordingly.
3. A copy of this order is available on the Internet and can be accessed at
www.ap.gov.in/goir.
BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer, Panchayat Raj, RIAD, Hyderabad.
The Superintending Engineer, Panchayat Raj, Warangal district.
Copy to:
The PS to Minister (Panchayat Raj & RWS)
Sc / Sf
//FORWARDED::BY ORDER//
SECTION OFFICER