GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
NABARD RIDF XV – Prakasam district – Providing BT surface to the road
from Chilakapadu to M.Vemulapadu - Granting of post facto Extension of
agreement time upto 30.9.2011 with out imposing the liquidated damages -
Orders – Issued
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x
PANCHAYAT RAJ AND RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 279 Dated:16.2.2012
Read the following:
1. G.O.Rt.No.1845,PR&RD(Progs.II)Dept,dated.11.12.2009
2. From the CE, PR, NABARD Hyd, Lr.No.NB10/ P/ RIDF/
PKSM/ Chilakapdu/ 2009, dated.19.01.2012.
.
*****
ORDER:
In the circumstances reported by the Chief Engineer, Panchayat Raj,
NABARD, Hyderabad in his letter 2nd read above, Government after careful
examination of the proposal, hereby grant post facto Extension of Agreement
Time up to 30.9.2011 i.e for (156) days without imposing liquidated damages,
in respect of work, “Providing BT surface to the road from Chilakapadu to
M.Vemulapadu” in Prakasam district sanctioned under NABARD RIDF - XV as
the delay was not attributed to the contractor.
2. The Chief Engineer, Panchayat Raj, NABARD, Hyderabad, is requested to
take necessary action accordingly.
3. A copy of this order is available on the Internet and can be accessed at
www.ap.gov.in/goir.
BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer, Panchayat Raj, NABARD, Hyderabad.
The Superintending Engineer, Panchayat Raj, Prakasam district.
Copy to:
The PS to Minister (Panchayat Raj & RWS)
Sc / Sf
//FORWARDED::BY ORDER//
SECTION OFFICER