GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
NABARD – RIDF XVI – Warangal district – Road from Nawabpet R & B
Road to Kothapally via Bhikyathanda of Lingala Ghanpur (M)– Granting of
Extension of agreement time up to 31.3.2012 without imposing the
liquidated damages- Orders – Issued.
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
PANCHAYAT RAJ AND RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 318 Dated:24.2.2012
Read the following:
1. G.O.Rt.No.1138, PR&RD (Progs.II) Dept, dt.2.8.2010.
2. From the Chief Engineer, Panchayat Raj, Lr. No.NB 19 /
Nawabpet /WGL/ 2010-11, dated. 7.2.2012
*****
ORDER:
In the circumstances reported by the Chief Engineer, Panchayat
Raj, NABARD, Hyderabad in his letter 2nd read above, Government after
careful examination of the proposal, hereby grant Extension of Agreement
Time up to EOAT up to 31.3.2012 i.e (145) days without liquidated
damages, in respect of work, “Road from Nawabpet R & B Road to
Kothapally via Bhikyathanda of Lingala Ghanpur (M)” in Warangal district
sanctioned under NABARD RIDF-XVI as the delay was not attributed to the
contractor.
2. The Chief Engineer, Panchayat Raj, NABARD, Hyderabad, is
requested to take necessary action accordingly.
3. A copy of this order is available on the Internet and can be accessed
at www.ap.gov.in/goir.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer, Panchayat Raj, NABARD, Hyderabad.
The Superintending Engineer, Panchayat Raj, Warangal district.
Copy to:
The PS to Minister (Panchayat Raj & RWS)
Sc / Sf
//FORWARDED::BY ORDER//
SECTION OFFICER