GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
PMGSY – Mahabubnagar District - Phase VI – “Providing BT on Road from
Kothur to Lingamdhana in Mahabubnagar District” - Revised
Administrative Sanction along with price escalation charges – Sanction –
Accorded – Orders – Issued.
-----------------------------------------------------------------------------------
PANCHAYAT RAJ & RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 369 Dated:03-03-2012
Read the following:-
1) G.O.Rt.173,PR&RD (progs.II) Dept.dt. 28.4.2007
2) Govt.Memo.No.9614/progs.II(2)/08,PR&RD,Progs.II
Dept. dt. 14.10.2008(Issued with the concurrence of
Finance (Expdr.PR&RD) Department vide their
U.O.No.22193/314/Expdr.PR&RD/08,dt.4.9.2008)
3) From the Chief Engineer, PR, PMGSY , Hyderabad ,
Lr.No.W23/DEE-III/PMGSY-Ph- VI- 1215/RAS,
dt. 23.03.10 and dated 28-1-2012.
<<>>
O R D E R:
In the reference first read above, orders were issued according
Original Administrative Sanction for an amount of Rs. 437.84 lakh in
respect of the work “Providing BT on Road from Kothur to Lingamdhana in
Mahabubnagar District” under PMGSY Phase VI.
2. In the reference 2nd read above, Government have issued orders
permitting for Price Escalation Charges and Excess Tender Premium for all
Phase VI Programme and also indicated therein the total amount required
for all Phase VI Works, with the concurrence of Finance(Expr.PR&RD)
Department, vide their U.O. No.22193/314/Expr.PR&RD/08, dated.
4.9.2008.
3. In the references 3rd read above, the Engineer-in-Chief, Panchayat
Raj, PMGSY, Hyderabad has requested the Government for according
Revised Administrative Sanction for Rs.435.43 lakh as against the Original
Administrative Sanction of Rs.437.84 lakh in respect of the work
“Providing BT on Road from Kothur to Lingamdhana in Mahabubnagar
District” under PMGSY Phase VI due to price escalation of Rs. 14.81 lakh.
4. Government after careful examination of the proposal, hereby accord
Revised Administrative Sanction for an amount of Rs.435.43 lakh (Rupees
Four crore thirty five lakh and forty three thousand only) indicating the
GOI Share of Rs.420.62 lakh (Rupees Four crore twenty lakh and sixty two
lakh only) and State share of Rs.14.81 lakh (Rupees Fourteen lakh and
eighty one lakh only) in respect of the work “Providing BT on Road from
Kothur to Lingamdhana in Mahabubnagar District” as against the Original
Administrative Sanction of Rs.437.84 lakh (Rupees Four crore thirty
seven lakh and eighty four thousand only) under PMGSY Phase VI due to
price escalation to be borne by the State Government as per the PMGSY
guidelines.
p.t.o.::2::
The amount chargeable is as follows:-
Original Administrative Sanction : Rs. 437.84 lakh
Now RAS required as follows:
a) Amount chargeable from PMGSY
Phase –VI : Rs. 420.62 lakh
b) Amount Chargeable from State
Govt. share towards price escalation : Rs. 14.81 lakh
Total RAS required (a+b) : Rs. 435.43 lakh
5. The Engineer-in-Chief, Panchayat Raj, PMGSY, Hyderabad is
requested to check the price escalation calculations to arrive at the actual
price escalation amount and take necessary action accordingly.
6. A Copy of this order is available on the internet and can be accessed
at www.ap.gov.in/goir.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Engineer-in-Chief, Panchayat Raj, PMGSY,Hyderabad
The Superintending Engineer, Panchayat Raj, Mahabubnagar Dist.
The District Treasury Officer, Mahabubnagar District.
The Account General, AP, Hyderabad.
Copy to:
The PS to M (PR&RWS)
Sc/Sf.
//FORWARDED BY ORDER//
SECTION OFFICER.