GOVERNMENT OF ANDHRA PRADESH
ABSTRACT
NABARD – RIDF XII – Chittoor–Construction of Causeway across
Kushastali river on road from Sathrawada to Mittapalem – Granting of
Extension of agreement time up to 31.07.2012 without imposing the
liquidated damages - Orders – Issued.
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
PANCHAYAT RAJ AND RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Rt.No. 414 Dated: 12.03.2012
Read the following:
1. G.O.Rt.No.1689, PR&RD (Progs.II) Dept, dt.25.11.2006.
2. G.O.Rt.No.1752, PR&RD (Progs.II) Dept, dt.08.12.2006
3. From the CE, PR, Hyd, Lr.No.NB6/4708/RIDF XII/ CTR/
2008, dated.14.2.2012.
*****
ORDER:
In the circumstances reported by the Chief Engineer, Panchayat
Raj, NABARD, Hyderabad in his letter 3rd read above, Government after
careful examination of the proposal, hereby grant Extension of Agreement
Time up to EOAT up to 31.7.2012 without liquidated damages, in respect
of work, “Construction of Causeway across Kushastali river on road from
Sathrawada to Mittapalem ” in Chittoor district sanctioned under NABARD
RIDF-XII as the delay is not attributed to the contractor.
2. The Chief Engineer, Panchayat Raj, NABARD, Hyderabad, is
requested to take necessary action accordingly.
3. A copy of this order is available on the Internet and can be accessed
at www.ap.gov.in/goir.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
C.R.BISWAL
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Chief Engineer, Panchayat Raj, NABARD, Hyderabad.
The Superintending Engineer, Panchayat Raj, Chitoor district.
Copy to:
The PS to Minister (Panchayat Raj & RWS)
Sc / Sf
//FORWARDED::BY ORDER//
SECTION OFFICER